Upgraded Internet Connection

McDowell County Schools Bandwidth Graph
 
On May 26th, 2017 we meet the requirements for to upgrade our internet connection from 1 Gbps to 2 Gbps. To get the full 2 Gbps, the following equipment needs/needed to be upgraded
 

Firewall

Cisco ASA 5555

List Price $18,000

MCS Cost: $0

 

Router

Cisco ASR 1001-X

List Price: $17,000
MCS Cost: $0
 

Filter

  Lightspeed with New Hardware Lightspeed Cloud Zscaler
Hardware Cost $17,000 $0 $0
Software Cost $19,200 $19,200 $0
Total Too Much Too Much Just Right
 
Sometime in the fall (before Dec 20th), we will switch over to Zscaler.

Upgraded Network Hardware

Project Cost $257,860.43
MCS Cost: $0
 
McDowell High School
 
Alternative Education Center
 
East McDowell Middle School
 
West McDowell Middle School
 

Future Upgrades to Network Hardware

Project Cost: $458,968.80
MCS Cost: $0
 
All the elementary schools.  This will include all new switches.  All schools will get access points, but it may not be enough to swap every AP.

Elementary Technology Assistant Curriculum

Digital Citizenship
Typing
G Suite
WeVideo

Digital Learning Competencies

On June 1, 2017, the Digital Learning Competencies for Teachers and for Administrators were approved by the State Board of Education (SBE) as part of licensure renewal requirements per G.S.115C-296(b)(1)c. This policy for Licensure Renewal (LICN-005) includes the requirement of two Digital Learning Competency CEUs and will go into effect for teachers and for administrators with licenses expiring on or after June 30, 2019.
 

Media Coordinators

The philosophy of McDowell County Schools' Media is to provide instructional resources, print and non-print, which will best prepare students for a meaningful and productive place in society. 
 
NCSLMA Conference: Oct 4th-6th
 
Align the MakerSpaces